SolUnesco retrospective process-regime gate
Current state: first retrospective measurement priority, but process-regime qualification is required before shadow design.
The four-project Southern Company financing is publicly bounded, and Southern Companies share a common OATT family. April 2025, however, is an Order No. 2023 transition period with transitional and annual-cluster process states.
Do not infer the four project names or regimes from public queues. A future zero-data step must bind each financed project to an explicit regime/version. Mixed regimes must be measured separately.
This is not a pilot, price or value claim. Public process facts contribute $0 buyer value.